Sunday 30 March 2014

Weekly Progress Report - 24/03/14 - 30/03/14


Safe to say this week has seen a lot completed and a lot left to do!

The Permanent way team has seen to the branch; now back in action at Steeplehouse, brushing up on a few jobs left regarding joints and sleepers, these jobs however will have to wait as our re-stock of sleepers won’t arrive till Thursday. This left the mainline to see to, with a full track inspection completed today, the work will now be carried out.

In the Motive Power Department, ZM32 was laid up with a small fuel leak, which left only start up and stop methods to try and find the leak, the leak was partly cured, and will be seen to at a later date. Later in the day it was decided that both Hibberd 4008 and L10 should be moved to the Carriage and Wagon Shed for storage while Manrider 104 is brought and housed in the engine house at Steeplehouse.

In rolling stock news, Manrider 104 held the main limelight, with the whole vehicle being lifted in order to release the rear axle for inspection of a possible faulty wheel bearing, it was later found to be the axle box assembly that wanted work completing on it, this will be completed during this next week.

An all together busy weekend!
Greenbat and the test train

ZM32 moving Hibberd 4008

ZM32 resting at Steeplehouse

Manrider 104 raised into the air to allow for the axle to be removed